Highland Logistics Terminal - Project

Highland Logistics Terminal - Project

Location

MANILA, PH

Status

Ongoing

Size

28,000 m²

Type

Distribution Center

Working Days

580 Working Days

Overview

Highland Logistics Terminal is a large-scale logistics and distribution hub built to optimize supply chain operations. Spanning 28,000 m², the facility includes high-capacity warehouses, docking bays, and heavy-load flooring for efficient cargo handling. Its layout supports large-scale vehicle movement with wide driveways and multiple access points. Integrated technology systems enable inventory tracking, automated handling, and real-time logistics monitoring. Administrative offices and staff amenities are included to support operations within the complex. Safety is reinforced with fire suppression systems, emergency protocols, and surveillance across the premises. Sustainable practices such as energy-efficient lighting and water recycling contribute to eco-friendly operations. Strategically positioned near major highways and industrial corridors, it provides easy connectivity to regional and national supply chains. The terminal is designed to handle large volumes, making it a key node in modern logistics infrastructure.

Projects Highlights:

  • High-clearance warehousing with heavy-load flooring

  • Multiple loading docks for efficient freight handling

  • Advanced fire suppression and safety systems throughout

  • Climate-controlled storage zones for sensitive goods

  • On-site administrative and staff facility blocks

  • Reinforced steel structure built for long-term durability

  • Dedicated truck and heavy-vehicle circulation routes

  • Energy-efficient lighting and ventilation systems

Project Milestones

Construction
March 2022

Groundbreaking Ceremony & Site Preparation

The project officially began with a formal groundbreaking ceremony attended by key stakeholders, local authorities, and project partners. Site surveys, geotechnical analysis, and environmental assessments were carried out to ensure the location met all regulatory requirements.

Construction
May 2022

Foundation Laying & Structural Planning

After the initial preparation, teams began pouring concrete and installing reinforcements for the foundation. This phase was critical to ensure long-term structural integrity and safety, with engineers conducting repeated testing of materials to meet seismic standards.

Construction
July 2022

Structural Framing & Core Construction

With the foundation cured and ready, construction crews moved into the framing stage. Steel beams, columns, and floor slabs were erected level by level, giving the project its first visible form, with internal core elements built simultaneously.

Construction
September 2022

Exterior Walls & Roofing Installation

This phase brought a dramatic change to the structure's appearance as exterior walls, insulation panels, and windows were installed. Roofing materials were layered for maximum durability, and sustainable materials were integrated throughout.

Construction
November 2022

Facade Completion & Interior Development

The exterior was completed with sleek finishes, giving it a professional and contemporary look. Inside, partitions, ceilings, and flooring installation began alongside lighting, HVAC, and smart building management systems.

Professional Team

View all Members
Natalia Rivera
Natalia Rivera

Client Relations Head

Victor Almeida
Victor Almeida

Carpenter Assistant

Nizahr Gems
Nizahr Gems

Founder, CEO

Alexei Morozov
Alexei Morozov

Civil Engineer

Get in touch with us

We're here to answer your questions, discuss your ideas, and bring your project to life.